Financier | Commitments |
---|---|
Ida Grant | 25.00 |
International Development Association (Ida) | 25.00 |
P160230
Active
Sandra Sargent
Ministry of Economy and Finance
Central Asia
(as of board presentation)
March 20, 2018
US$ 50.00 million
Ministry for Digital Development
2018
US$ 50.00 million
B
October 29, 2021
May 31, 2023
Yes
Financier | Commitments |
---|---|
Ida Grant | 25.00 |
International Development Association (Ida) | 25.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | Investment Project Financing |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Financier | Approval Date | Closing Date | Principal | Disbursed | Repayments | Interest, Charges & Fees |
---|---|---|---|---|---|---|
IDA62000 | March 20, 2018 | May 31, 2023 | 25.00 | 0.00 | N/A | N/A |
IDAD2790 | March 20, 2018 | May 31, 2023 | 25.00 | 1.53 | N/A | N/A |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar, 2018 | IDA62000 | Commitment | 25,000,000.00 |
Mar, 2018 | IDAD2790 | Commitment | 25,000,000.00 |
Mar, 2019 | IDAD2790 | Disbursement | 200,000.01 |
Jul, 2019 | IDAD2790 | Disbursement | 800,000.00 |
Dec, 2019 | IDAD2790 | Disbursement | 320,799.68 |
Oct, 2020 | IDAD2790 | Disbursement | 209,907.90 |
PREVIOUS RATINGS | CURRENT RATINGS: 03-23-2021 | |
---|---|---|
Progress towards achievement of PDO | Moderately Unsatisfactory | Moderately Unsatisfactory |
Overall Implementation Progress (Ip) | Moderately Unsatisfactory | Unsatisfactory |
N/A | N/a | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to the Internet | Value | 0.00 | 0.00 | 1563000.00 |
Date | December 31, 2017 | December 31, 2019 | December 31, 2022 | |
Comment |
Internet penetration (%) | Value | 34.50 | 40.00 | 60.00 |
Date | December 31, 2017 | December 31, 2017 | December 31, 2022 | |
Comment |
Private sector investments committed through the project (US$) | Value | 0.00 | 0.00 | 60000000.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
E-Services and applications utilizing the shared services platforms | Value | 0.00 | 0.00 | 20.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
International Internet bandwidth per capita (kilobit per second per person) | Value | 21.30 | 21.30 | 60.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Average retail price for 1 GB prepaid mobile data package (US$) | Value | 4.65 | 0.10 | 2.50 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of fiber-optic network | Value | 16281.00 | 28784.00 | 17281.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Number of government agencies using the G-Cloud shared infrastructure | Value | 0.00 | 0.00 | 30.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Policy, legal and regulatory documents developed and submitted to the Government under the project (new and amended) | Value | 0.00 | 0.00 | 30.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
M&E Surveys | Value | 0.00 | 0.00 | 10.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Number of cross-border fiber-optic links | Value | 7.00 | 7.00 | 10.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Number of visitors per year to State Portal of E-Services | Value | 0.00 | 1000.00 | 1000000.00 |
Date | September 4, 2020 | December 31, 2019 | December 31, 2022 | |
Comment |
People trained under the project | Value | 0.00 | 259.00 | 5000.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
of which government officials | Value | 0.00 | 165.00 | 3000.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
of which female | Value | 0.00 | 20.00 | 50.00 |
Date | December 31, 2017 | December 31, 2017 | December 31, 2022 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 1000000.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Of which female (%) | Value | 0.00 | 0.00 | 50.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Internet bandwidth pre-purchased by Government (Gbps) | Value | 0.00 | 0.00 | 10.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Digital transactions conducted on the State Portal of E-Services per year | Value | 0.00 | 0.00 | 1000000.00 |
Date | December 31, 2017 | September 4, 2020 | December 30, 2022 | |
Comment |
Wholesale Transit Pricing per Mbps per month | Value | 22.00 | 7.00 | 10.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
"Smart” data-driven solutions developed under the project | Value | 0.00 | 0.00 | 5.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Institutions and Government agencies connected to the Government Network (G-Net) | Value | 34.00 | 46.00 | 134.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Users satisfied with digital services supported by the project | Value | 0.00 | 0.00 | 80.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
of which satisfied with broadband services | Value | 0.00 | 0.00 | 80.00 |
Date | December 31, 2017 | December 31, 2017 | December 31, 2022 | |
Comment |
of which satisfied with e-services | Value | 0.00 | 0.00 | 80.00 |
Date | December 31, 2017 | December 31, 2017 | December 31, 2022 | |
Comment |
Partnerships formed under the project | Value | 0.00 | 6.00 | 30.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |
Communication and public outreach events | Value | 0.00 | 15.00 | 50.00 |
Date | December 31, 2017 | September 4, 2020 | December 31, 2022 | |
Comment |